HMRC – NCTS5 Implementation Update

To help traders prepare for the introduction of NCTS5, HMRC is issuing regular updates which via Gov.uk.

The latest update provides information on:

– Implementation of NCTS5 and downtime

– Business Continuity/ fallback

Please see the attached document and the update received from HMRC.

Implementation of NCTS5 and downtime

To ensure the transition from NCTS4 to NCTS5 in Northern Ireland (NI) and Great Britain (GB) takes place with minimal disruption for traders, the changes will be taking place on separate dates as follows:

  • Friday 28 June – NCTS5 in NI (XI)
  • Monday 1 July – NCTS5 in GB  

Some providers of commercial software will be switching their software from NCTS4 to NCTS5 on 1 July to ensure this takes place after both changes have been implemented.

Commercial software providers should be contacting clients to confirm where they cannot switch over their NCTS5 software until 1 July 2024.However, it is recommended that businesses proactively check with their providers in advance of 28 June 2024.

Friday 28 June 2024

The XI service will be unavailable from 09:00 – 16:00 British Summer Time (BST), for approximately 7 hours.

Before this time, you will need to: –

  • Discharge all arrivals, where possible, to avoid delays as HMRC needs to do this manually while the system is unavailable.
  • Make sure you have received the Release for Transit notification for any submitted declarations in order to move the goods.

If your software provider cannot switch from NCTS4 to NCTS5 until 1 July, you should: –

  • Submit and release before 09:00 on 28 June, all XI declarations for goods moving on 28, 29, or 30 June and 1 July, if you are an Authorised Consignor.
  • Re-plan your movement of goods to avoid 28, 29, 30 June and 1 July if you are moving goods under the Normal procedure; or
  • Use the Web portal following the downtime on Friday 28 June to submit declarations.

Monday 1 July 2024

The GB service will be unavailable from 06:00 to 13:00 (BST), for approximately 7 hours.

Before this time, you will need to: –

  • Discharge all arrivals, where possible, to avoid delays if HMRC needs to do this manually while the system is unavailable.
  • Submit and release all declarations for goods moving on 1 July, if you are an Authorised Consignor/Consignee.

While NCTS is down, you should refrain, where possible, from moving goods under the Normal procedure which requires attending Inland Border Facilities (IBFs) or ports to start movements.

Please note:

  • While NCTS4 in XI is unavailable, the GB NCTS4 service will still be online and available to submit declarations.
  • While NCTS4 in GB is unavailable, the new XI NCTS5 will be online and available to submit declarations.

Important

If you must move goods and have been unable to submit the declarations prior to the start of system downtime, you will be able to use the existing manual fallback procedure, although we recommend you do not travel to an Inland Border Facility (IBF) to start a transit movement until the system is available. You can find the manual fallback process in the Transit Manual Supplement.

Please find attached further important information relating to our cutover to NCTS5.

Please look out for our webinar on 19 June 2024 at 13.00 where we will cover the downtime and business continuity subjects above in more depth.

You can join the webinar using the following link: –

NCTS5 Webinar 3 190624

HMRC will issue communications and update our service availability page to confirm when each service has successfully gone live.